- waiting for authorities to sign an agreement regards to location permit for Kupres and Ljubusa
- PPA agreement with operater
- first phase (aprox. 100 MW) final design and building permit approval
- grid connection study and grid connection approval
- finance construction project (cca 1.350.000 €/MW) for the first phase)
- next phases of technical development
Wind farm project
Pakline-Ljubusa-Kupres